Section 3-South Building -Hydro- jetted and televised the main 8" pipe from the manhole near the gym entrance door approximately 300' upstream to the manhole inside the new auxiliary gym. -Flushed all loose scale and debris from the line. More than 40 gallons of scale and debris were removed. -Televised the branch line from the first girls toilet in room G-188 60' to 8". Main line was clear. Ties into 8" main 12' downstream at the cleanout in the girls PE office, room F165. -Televised form the boys and girls PE office bathroom toilets. Blockage at 45' from Boys PE office toilet. -Cut lead out with the Miller and robotic cutter, 8" downstream from the girls PE office toilet. -Televised 75' to the wye from the girls locker room. *All PE offices; girls and boys locker room bathrooms tie into the rise of the cleanout in F165. -Televised the branch line from the STEP bathroom 60' to 8". Main line was clear. Ties in the 8" main 60' downstream of the inside manhole near the auxiliary gy