Install new Honeywell water valve actuator. HP4 Install and test run discharge line water valves electronic actuator Remove equipment lockout tag and re-establish high voltage Confirm repairs to the alarm panel shutdown relay System is ready for control by the building automation system
Install Water Furnace 5 Series Geothermal system. 2 Stage compressor, Variable Speed ECM blower Model #: W5AV036BD1A12CTL2B00 Serial #: 250701150 Left Side Return 3 Ton Package Efficiency: Up to 5.0 COP / 30.0 EER Features Included: *Aurora Advanced Controls *15KW Backup heat *2" Merv 11 air filter *Geo Link 1 pump non-pressurized loop flow center *Vision Pro 8000 WiFi thermostat Installation: *Install 3 Ton vertical closed ground loop. Installed By Jackson Geothermal. *Reconnect to existing high voltage electrical circuit *Transition to existing supply and return duct *Add 1 return air to basement Warranty: (Annual maintenance must be performed) Water Furnace 10 Year Parts Water Furnace 10 Year Labor Flow Center and Accessories 5 Year Parts and Labor Optional accessories: NuCalgon iWave Air Purifier - ADD $925 [Declined} Reusable/Washable Electrostatic Air Filter - ADD $175 [Declined] *** 30% Federal Tax Credit Eligible Disclaimer: No drill cuttings or water cleanup is included i
Install new OEM control board for HP-04 Replacement control board did not fix the problem. The low voltage fuse tripped instantly when high voltage power was a reapplied after the replacement part was installed Additional diagnostics confirms two problems 1- the discharge line water valve actuator has failed with a short to ground and is tripping the low voltage fuse instantly when power is applied to the Y circuit 2- the red smoke detector wire circuit that is in series with the 24vac hot "R" wire of the transformer does not have any continuity therefore not providing any power from the transformer to anything in the air handler The temporary transformer installed for testing purposes at the last service has been removed and will NOT be applied to the bill. The air handler ICM control board is non-refundable therefore the new board will remain in place and Eric has taken possession of the original control board Westin Air will order and replace the water valve actuator *Eric
Electrical short diagnostics Low volt transformer breaker is tripping instantly Install replacement transformer 75 VA 240vac Install replacement 35 UF compressor capacitor. Old at 29uf Trace electrical short to the red 20\2 wire in series with a transformer low voltage feed Remove integrated smoke detector shutdown wire that was in series with the R (hot) wire of the transformer. Run test equipment in cooling mode If equipment continues to run correctly and smoke detector company confirms a correct repair or a real breakdown, the transformer installed today can be swapped out for the original that is still on site in place at the next regular maintenance service *** Currently HP4 is running with no smoke detector shutdown and is a safety concern if there is a fire in the building Recommend addressing the repairs with the smoke detector company ASAP***
5-28-25 Cedar ridge Five system cooling season annual maintenance, tune-up, safety inspection. 3x lodge, 1x ranger station, 1x maintenance compound. All air filters in all five systems are in like new 3-week-old condition replaced by on-site maintenance crew. Inspect all blower systems and power supplies, flush drain systems and drain pans, test run all equipment in cooling mode, inspect batteries and thermostats, water flush outdoor condenser coils, inspect and test run All electronics on outdoor equipment, test all high voltage power supplies and starting relays. Install replacement blower capacitors, 370 volt power supplies, on the lodge right side Goodman, and Lennox All other cedar ridge equipment is running in very good condition no other recommendations or services required at this time Nature center Replace all air filters in all systems except both dehumidifiers and the new number 8 system that is not online yet Perform full cooling maintenance inspection, cleaning, and
Install WaterFurnace Versatec 300 Compact Horizontal (V3) 030 -208-230/60/1 Voltage - Model #: V3AH030BS0AN4DELBENN010SSS - Serial #: 250401884 Features Included: *Aurora BACnet Controller *Loop connection kit Installation: *Reconnect to existing water loop. *Reconnect to existing high voltage electrical circuit *Transition to existing supply and return duct Warranty: (Annual maintenance must be performed) WaterFurnace manufacturers parts warranty 1 Year Westin Air labor warranty Notes: This system is provided with an Aurora BACnet controller programmed to operate with Versatec 300 system. Please contact your controls contractor to determine if it will integrate with your current controls program.
AH #2 AV room on bamt Install replacement ECM blower motor 3/4 horsepower
Nature center HP2 (AV room bsmt) Blower motor locked up OEM equivalent replacement required due to unit specific programming Seth will consult with JP and order 3/4 horsepower ECM constant torque 208/230 indoor blower motor
DCA (dehumidifier corporation of America} Two systems both confirmed refrigerant leaks. System two in the North main front door lobby System one to the south in the main lobby area has visible oil staining on the cooling\dehumidification coil and refrigerant pressures are running very very low. 48 and 143. System is producing an air temperature change from 72.5°f return to 77.1° with a minimal humidity reduction from 63.4% to 57.3%RH. System 2 at the main front doors is not running at all due to 0 PSI of refrigerant R407C After discovering 0 PSI and possible die on the cooling / dehumidifying coil nitrogen pressure confirmed the leak with soap bubbles and video Both systems need air coils replaced The south system is still running with low refrigerant pressure The north system has the power turned off and will not run is it uploading I knew 10 or 15 minutes it might take it Seth will consult with JP and prepare estimates for repair and replacement All equipment in the buildin
Recover all of refrigerant, remove and replace thermostatic expansion valve and liquid line filter dryer, nitrogen pressure test, evacuation micron test to 700 microns, recharge with 81 oz new R410A The heating refrigerant circuit is running in very good condition at this time with acceptable refrigerant pressures 21 PSI higher than running test pre-part replacement. Running pressures before 68\345 Running pressures after 89\335 @ 42°incoming pressurized ground loop and producing 94° supply temperature with 67 return
Cooling circuit has a actively failing thermostatic expansion valve dropping the suction pressure to below 60 with 40 superheat. The addition of refrigerant for testing purposes only increased the discharge pressure from 330 up to 380 while suction pressure continued to drop. Carrier climate Master system needs new heating TXV, refrigerant line filter dryer, 81 oz new R410A Removed compressor shipping brackets Seth will contact climate Master and prepare estimate for homeowners 50YD049JCB301 3608V61365
Daikin Fit system Noise concern Sound they are hearing is the EEV (electronic expansion valve) doing a self-test. Demonstrated it by resetting the power to the furnace, which causes the valve to go through the test. System is operating normally at this time.
Replace gas valve on Goodman furnace number 1 in lodge. Replace gas valve on Bryant 80% furnace in Old Barn. Replace gas valve on North maintenance shop hot dawg heater. Replaced three gas valves. Installed propane conversion kits, and set Manifold gas pressures to manufacturers specifications. Test ran in heat mode to test operation and temperature rise. All three properly running within temperature rise.
Furnace operating upon arrival. ADJUSTED BLOWER SETTINGS DUE High static pressure..VERIFIED OPERATION WITH CLIENT and set up account for Daikin .System is operating normal at this time
Called through service Titan and spoke with Eric to discuss non-functioning shop heater. He will try a few things and let us know if he still needs a service call