Shawn B.

Shawn B.


Job Checkin

Return to complete quoted work. Dug up sewer line and waterline in front of house, between house and driveway. Waterline was dug up to install a ball valve, as existing gate valve has a snapped stem and gate does not function. Upon digging, we discovered the main line before the valve is galvanized waterline. After gate valve is copper one inch main pipe. Due to small space and restrictions, I rerouted the waterline to allow the installation of a ball valve, and installed a small box to avoid the valve being buried as the previous valve was. Slowly pressurized main line to pressurize building. Building pressurized over 10-15 minutes. Sewer line was dug up and replaced from near foundation to mainline 3-4 feet deep. We removed an additional section on site because it was so deteriorated that if fell apart during the course of work. New sewer is pvc, and a two way cleanout has been installed. Measurements notes on profile history if required for sewer replacement next year. Dig sit

Return to complete quoted work.

Dug up sewer line and waterline in front of house, between house and driveway. 

Waterline was dug up to install a ball valve, as existing gate valve has a snapped stem and gate does not function. Upon digging, we discovered the main line before the valve is galvanized waterline. After gate valve is copper one inch main pipe. Due to small space and restrictions, I rerouted the waterline to allow the installation of a ball valve, and installed a small box to avoid the valve being buried as the previous valve was. Slowly pressurized main line to pressurize building. Building pressurized over 10-15 minutes. 

Sewer line was dug up and replaced from near foundation to mainline 3-4 feet deep. We removed an additional section on site because it was so deteriorated that if fell apart during the course of work. New sewer is pvc, and a two way cleanout has been installed. Measurements notes on profile history if required for sewer replacement next year.

Dig sit Return to complete quoted work.

Dug up sewer line and waterline in front of house, between house and driveway. 

Waterline was dug up to install a ball valve, as existing gate valve has a snapped stem and gate does not function. Upon digging, we discovered the main line before the valve is galvanized waterline. After gate valve is copper one inch main pipe. Due to small space and restrictions, I rerouted the waterline to allow the installation of a ball valve, and installed a small box to avoid the valve being buried as the previous valve was. Slowly pressurized main line to pressurize building. Building pressurized over 10-15 minutes. 

Sewer line was dug up and replaced from near foundation to mainline 3-4 feet deep. We removed an additional section on site because it was so deteriorated that if fell apart during the course of work. New sewer is pvc, and a two way cleanout has been installed. Measurements notes on profile history if required for sewer replacement next year.

Dig sit