1-Year Water Conditioning Equipment Maintenance: Quarterly checkup on new Lancaster water treatment equipment. - Number of visits: 4 - Salt shall be added to brine tank on each visit at up to (10) 50 pound bags. - Sediment filter cartridge shall be changed once every 3rd visit at 9 month mark. - Water sample shall be taken and tested to verify unit is operating as should. - 10% off all plumbing services within building. 5-27-2025, completed initial maintenance checkup, tested water using technician test kit and found the hardness was 0, found no iron in the water at the time and the PH content was 7.0 Ran system through softener cycles to visually inspect for any issues regaurding the system Salt Brine tank level is roughly 3/4 of the way full and will probably need to be refilled on the next visit