1-5-2026: Cleaned and measured sewer in preparation for lining 1-8-2026: Finished cleaning heavy roots and retrieving broken clay pipe and brass cap from line upstream of clean out, jetted heavy sediment and debris 20’ downstream of clean out out to city main at 44’. Lined sewer downstream 44’ to city main starting liner in 6” pvc just downstream of clean out and ending liner just short of city main. ***We will return to line sewer 91’ upstream of clean out starting liner near clean out and ending liner just short of 4” cast and install 6”x5’ spot repair liner at last joint before 4” cast also Reinstate 7 connections. 2-12-26 Lined sewer from outside cleanout upstream approximately 91’ starting liner near cleanout and ending liner just short of 4” cast. Installed 2 6”x5’ spot repair liners at last joint before 4” cast. Reinstated 7 connections.