1/12/26: Cut out combination of cast, copper, and pvc drain lines from the kitchen in the crawlspace. Stubbed out a new drain in the kitchen cabinet and ran three inch pvc to the other side of the crawlspace. Replaced water heater with a 50 gallon lowboy. Will return tomorrow to finish the last of the work quoted for the drain repipe. Made customer aware that the existing cast for the washing machine coming through the foundation is coming out evenly pitched and slightly lower than needed. Due to this, we can’t correct the slope of the existing line. 1/13/26: Returned and finished the under sink plumbing for the kitchen and guest bathroom. Pulled both toilets and replaced through the floor with pvc. Cut out all drain piping below the house. Connected the kitchen and guest bathroom bathroom to the main in new pvc. Capp new line going back towards the master bath. Will connect that bathroom group tomorrow on return. Made customer aware that pipes aren’t connected below any of the maste