Tuesday, July 23, 2024 Excavated on the east side of the building to expose the cast-to-clay connection. Cleaned and descaled the sewer line in preparation of lining. Televised and measured the sewer line following cleaning. Wednesday, July 24, 2024 Inserted a 4” liner through the 4” stack in Unit E extending downstream approximately 90’ to open excavation east side of building Inserted a 6” liner through the open excavation extending downstream approximately 50’ to the city main. Reinstated 4 - 4" stack connections and 4-2” laundry connections. Thursday, July 25, 2024 Installed a 6" clean-out at the cast to clay connection and bedded the pipe in stone. Backfilled the hole.