Job Checkin

5-12-2023: installed 5’x6” spot repair liner with LR3 at hole in clay tile near main, also installed a 5’x6” spot repair liner about 15’ downstream of clean out where hole on left hand side of pipe was. Collected $4190.00 for x2 spot repair liners that were installed on 5-11-2023. -If inversion lining is installed no later than July, 2023 the original balance of $4,190 will be due upon completion. -If inversion lining is installed between August, 2023-June, 2024 the cost will increase by $1,690 (cost of 2nd spot repair installed on 5/12/23) for a total due of $5,880.00.