8-18-2025: Cleaned and measured measured sewer in preparation for lining from 4” overhead stack 123’ to just short of city main. 8-19-2025: lined sewer from 4” overhead stack clean out in basement 123’ downstream to city main starting liner in 4” pvc near stack and ending in 6” clay just before city main. Reinstated x4 connections x3 6” tie ins from bathrooms/kitchen at 11’, 36’, and 87’ and x1 2” kitchen connection near stack.